Field guide + connection service — not a contractorLittleton, Massachusetts · Rt 2 / I-495 corridorLog checked October 2026
Littleton Concrete Cutting
The Cut Log — a local guide to cutting, coring & scanning

Log entry 06 — Selective demolition & removal

Selective demolition and removal: the cut is half the job

Cutting separates concrete. Demolition and removal take it away — in pieces small enough to handle, through a building that may be occupied, to a lawful destination. Scoping removal separately and explicitly is what prevents the classic surprise: a neat pile of 800-pound slab sections and nobody contracted to move them.

What “selective” means

Selective (interior/strip-out) demolition removes defined elements — a slab panel, a wall section, a stair, a equipment pad — while protecting everything that stays: structure, finishes, MEP systems, and the occupants on the other side of the plastic. It is surgical work done with saws, small breakers, carts, and dust control, not an excavator through a wall. The cut lines from the sawing pages are the demolition plan's boundaries.

The weight problem, in numbers

PieceApprox. weightHandling implication
Slab section 2 ft x 2 ft x 4 in.~200 lbTwo-person carry or cart; the largest sensible hand piece
Slab section 4 ft x 4 ft x 6 in.~1,200 lbMachine, gantry, or cut it smaller — nobody hand-carries this
Wall panel 3 ft x 7 ft x 8 in.~2,100 lbLowered by equipment in sections; never dropped and broken in place indoors
Core, 12 in. dia. x 8 in.~60 lbOne person, with a grip plan — cores are round and roll

Concrete weighs about 150 lb per cubic foot. Every removal quote is secretly a weight-and-path quote: piece size, carry distance, stairs or elevator, door widths, and where the truck can stand.

Disposal, Massachusetts edition

  • Clean concrete (unpainted, uncoated) is recyclable — crushed for aggregate at local facilities; clean loads cost less to place than mixed debris.
  • Mixed construction debris goes to a licensed C&D facility with transfer-station fees by weight; Massachusetts bans disposal of clean concrete and similar materials in solid-waste landfills where recycling applies — expect the quote to separate haul from disposal fees.
  • Slurry is not debris and not drain water. Wet-cut slurry is vacuumed, contained, and disposed of as a liquid/solid waste per its character — never washed to a storm drain or sanitary line without permission. See the silica and slurry log.
  • Older buildings: coatings, adhesives, and adjacent materials can trigger asbestos or lead rules (mill-era buildings especially). Suspect material stops demolition until it is surveyed — a legal requirement, not a preference.

Scope it in writing

A removal scope should state: what is removed, piece-size/handling method, path of egress, floor and finish protection, dust containment level, haul and disposal inclusion, patch-back or leave-ready condition, and who backfills a trench. If a cutting quote says only “cut and remove,” ask which of those lines it covers. The request form asks removal as its own question for exactly this reason.