Field guide + connection service — not a contractorLittleton, Massachusetts · Rt 2 / I-495 corridorLog checked October 2026
Littleton Concrete Cutting
The Cut Log — a local guide to cutting, coring & scanning

The ledger — Cost guide + Cut Planner

What concrete cutting costs around Littleton — printed, with the arithmetic showing

These are planning ranges for the Greater Boston / Middlesex County market, checked October 2026, stated with their assumptions. They are not quotes and not a contractor's price list. Their job is narrower and more useful: to let you plan, compare a quote's shape, and spot the line item a too-cheap quote has quietly left out. The Cut Planner below computes from exactly these printed numbers — change an input and the arithmetic it prints is the arithmetic you can re-check by hand.

The printed rate ledger

WorkUnitPlanning rangeAssumptions printed with the rate
Core drilling — 2 in. diameterper hole$140 – $210Floor work, first 8 in. of depth included
Core drilling — 4 in. diameterper hole$185 – $280Floor work, first 8 in. of depth included
Core drilling — 6 in. diameterper hole$240 – $360Floor work, first 8 in. of depth included
Core drilling — 8 in. diameterper hole$320 – $480Floor work, first 8 in. of depth included
Core drilling — 12 in. diameterper hole$480 – $720Floor work, first 8 in. of depth included
Core drilling — depth beyond 8 in.per added inch, per hole$18 – $27Applies to each inch over 8, each hole
Slab sawing — slab to 6 in. thickper linear ft$14 – $22Cured concrete, exterior or open floor
Slab sawing — slab 7–9 in. thickper linear ft$20 – $31Cured concrete
Slab sawing — slab 10–12 in. thickper linear ft$28 – $42Cured concrete; thicker work quoted per job
Wall sawing — wall to 8 in. thickper linear ft$38 – $58Track-mounted; price follows opening perimeter
Wall sawing — wall 9–12 in. thickper linear ft$52 – $78Track-mounted; thicker walls quoted per job
Reinforcement adjustment — welded meshmultiplierx 1.10Applied to the cutting subtotal
Reinforcement adjustment — rebarmultiplierx 1.25Applied to the cutting subtotal; post-tension is never multiplied — it stops the job for scanning
Restricted access adjustmentmultiplierx 1.20Stairs/lift access, long hose runs, hand-carried equipment
Interior slurry control — coringflat per visit$75 – $120Containment, wet vacuum, finish protection
Interior slurry control — sawingflat per visit$120 – $200Containment, wet vacuum, finish protection
Mobilization minimumper visit$450 – $650Floor under every job: truck, operator, first setup. Small jobs bill at the minimum

Not in the ledger, deliberately: wire sawing, chain sawing beyond corner finishing, scanning visits, removal and disposal, patching, and engineering. Each is real scope with its own pricing logic, explained on its own page — a single blended “per foot” for them would be a fiction.

The Cut Planner

Pick the work, enter the measurements you have, and read the itemized range. Incomplete measurements produce a wider, honest answer — or, for post-tension, no answer at all, on purpose.

1 — Kind of cut
2 — Core details
3 — Reinforcement (the honest question)

“Unsure if PT” is treated as post-tensioned. That is deliberate.

4 — Access
5 — Setting

Planning range

With JavaScript off, the planner cannot compute — so plan from the printed ledger above: multiply your quantity by the rate band, apply the adjustments in order (reinforcement, then access, then the interior flat charge), and hold the total at or above the $450–$650 mobilization minimum. Every rate the planner uses is in that table; nothing else is used.

Worked example, by hand

Two 4-inch cores through an 8-inch rebar floor, interior. Ledger: 4 in. hole = $185–$280; depth 8 in. adds nothing (first 8 in. included). Two holes: $370–$560. Rebar x1.25: $462.50–$700. Interior coring slurry control: +$75–$120 → $537.50–$820. Mobilization minimum already exceeded at the top and the floor of $450 does not bind at the bottom after adjustments ($537.50 > $450). Planning range: about $540–$820. Run the same entries in the planner — it prints the same lines in the same order.

The factors that move a real quote

  • Thickness found vs thickness stated — a “6-inch slab” that is 9 inches at the cut reprices the per-foot band. Operators verify with a test core or edge.
  • Rebar size and congestion — mesh is a nuisance; #5 bars at 6 inches on center in two mats is a different day.
  • Greater Boston labor and mobilization — travel on Rt 2 / 495, parking, and site rules in occupied facilities are real time, priced as such.
  • Water, power, and disposal — sites that cannot supply water or power add a generator/water setup; slurry disposal requirements vary by facility.
  • Batching — the mobilization minimum is per visit. Every hole and cut list combined into one visit shares one minimum; three small visits pay it three times.

Turn a planning range into a real quote — request a connection